Submit a demolition notice

Demolitions

Under the Building Act 1984, you must notify Building Control if you intend to demolish a building or structure (or part of it) with a volume greater than 50m³.

Step 1 – Submit a Section 80 Demolition Notice

Notify us at least 6 weeks before demolition starts.

Your notice must include:

  • The address of the building the notice relates to
  • A clear description of the proposed demolition work
  • A site plan (scale 1:1250 or larger) showing the size and position of the building to be demolished
  • A Block plan showing the building to be demolished, in relation to neighbouring properties

Step 2 – Notify Utility Providers

Inform electricity, gas, and water suppliers about the demolition.

Step 3 – Inform Neighbours

Notify the owner(s) or occupier(s) of any adjoining properties.

Before You Start Work

You must not begin demolition until:

  • We have issued a Section 81 notice; or
  • Six weeks have passed since we received your Section 80 notice.

It is an offence to demolish a building without the necessary notice being given.

What We Do

On receipt of your demolition notice, we will:

  • Contact you for payment
  • Issue a Section 81 counter notice detailing conditions to ensure the work is carried out safely.

Fees

A fee of £260 is payable upon submission of a demolition notice. No VAT is payable.

Other Permissions to consider

You may also need:

  • Planning permission under the Town and Country Planning Act
  • Listed building consent or conservation area consent if the building is listed or in a conservation area—even if Building Act notice isn’t required.

Always check with your local planning authority.